The renovation is ninety-eight percent done. The walls are painted, the floor is down, and the front door still does not close properly. It catches on the frame, the latch needs a lift, and the reader responds only when the credential is held at an angle nobody will remember. The project is not finished; it is nearly finished, which is the most expensive state a building can be in.
This brief is for the people who have to close that gap: installers, integrators, project buyers and property operators handing a renovated entrance back to the people who will use it every day. It sets out why entrances slip through, a six-item walk that catches the usual misses, the measurements worth taking before anything goes on the list, and how to write an entrance renovation punch list that gets fixed.
Why entrances slip through
Trades finish in sequence, and the door is usually last. It is fitted after the frame is set and after the floor level is final. By the time the entrance is complete, most of the project team has moved on to the next building, and the people left on site are there to clean, not to test.
The door is also the first thing everyone uses. From the day the site barriers come down, staff, residents and visitors are opening it, leaning on it, and testing it in ways no commissioning sheet anticipated. A defect that would sit quietly on a back-of-house door becomes a daily complaint at the main entrance, and complaints arrive before the handover meeting does.
The result is a familiar pattern: the entrance is on the punch list, but the item is vague. “Adjust door” tells nobody what is wrong, what right looks like, or who is coming back to fix it. A punch list is not a complaint log. An entrance renovation punch list is a set of instructions for closing a project, and the entrance deserves better instructions than most.
The last five percent is the part users judge. A renovation is assessed at the entrance, not in the plant room. Whatever the schedule says, the door is the piece every occupant touches on day one, and it sets the tone for everything behind it.
The six-item walk
Walk the entrance with the door in normal use, not propped open for the tour. Six checks cover most of what goes wrong, and they take less time than the meeting about them.
- Swing. Open and release the door from several angles. It should close under its own weight, settle without a lift, and meet the strike without rubbing the frame. Renovation work moves frames, and a frame that moved after the lock was set will show up here.
- Latch. With the door closed, confirm the bolt extends fully into the strike and holds without rattle. Then open the door and repeat. A latch that works only when the door is pushed, or only when it is pulled, is not finished.
- Reader response. Present a credential at the pace a resident would, at the height a resident would, and confirm the same response every time. Test in the weather and light the entrance actually gets, not only on a quiet afternoon.
- Override. Operate the mechanical key override before handover, not during the first outage. The key should turn without forcing, the door should open, and the key should end up labeled in the place the building will look for it. The DS-series deadbolt is documented with a mechanical key override, and the handover is the moment to prove it works.
- Credentials. List every credential issued during the renovation, including the ones given to trades and temporary staff, and confirm which have been removed. A credential register that stops at the day the client moved in is not a register; it is a guess.
- Finish. Check the entrance as a set, not as separate parts. Scratches, inconsistent sheen and protective film left in place are all handover items, and they are easier to resolve before final payment than after it.

Measuring before you list
Some entrance defects are not adjustment problems. They are fit problems, and no amount of tweaking will close the gap. Before a punch item goes on the list, measure the door and compare it with the documented numbers for the lock that has to sit in it.
The DS-series deadbolt is documented to fit door thicknesses of 35 to 55 mm, with standard 60 mm and 70 mm backsets. Those three numbers answer most of the questions a fit issue raises: whether the door is inside the supported range, whether the backset matches the preparation, and whether the hardware specified for the opening can actually be installed on the door that arrived. The smart lock door compatibility guide sets out the measurements to take, and the same figures should appear on the spec sheet for the model being handed over.
Measure the door that is hanging, not the drawing that was approved. Renovations replace doors, adjust frames and change floor levels, and the opening at handover is often not the opening in the tender. A measurement taken from the drawing is a reason to check, not a substitute for checking.
Writing the punch item
A punch item that gets fixed has four parts and, ideally, a photograph. The difference between a list that closes and one that circulates for months is usually not the defect; it is whether the item gives the person returning to site enough to act on.
What every entrance item should contain
- Location: door name and floor, in the words the building uses. “Main entrance, north side” is better than “door 14” if door 14 means nothing to the person fixing it.
- Condition: what is happening now, described without interpretation. “Door catches on the strike side when released from 30 degrees” is checkable; “door sticks” is not.
- Expected state: what finished looks like. “Closes and latches from any opening angle without lifting” gives the person a test to pass.
- Who fixes: the trade or supplier responsible, by name, not the general contractor’s office. If two trades could own it, the item needs one owner and the other named as support.
- Evidence: a photo and the date taken, attached to the item. The photo is also the before image for the handover file.
- Close-out: who signs it off and what they will do to verify. A tick box is not verification; a repeat of the original test is.
The installer handoff packet is the natural home for the closed items, the credential register and the model documentation, so the building receives one folder rather than five.
After the list closes
Closing the punch list is not the end of the entrance. Three records should survive the handover and live with the building: a credential register, a documentation folder and a photo archive.
The credential register lists every card, fob and key issued, who holds it and when it was removed. The documentation folder holds the model sheets and spec sheets for the installed hardware, available from CaremLock on request, so the next person to service the door does not start from scratch. The photo archive records the entrance as handed over, including the inside of the frame and the strike, which a future contractor will want to see. A hardware photo archive built at handover takes an hour and saves an argument later.
None of these records is glamorous, and none will appear in the handover presentation. They are the difference between an entrance that was finished and one that will be finished again by somebody else, at the building’s expense.